Construction Bond Update: Building Our Future, April 2008
Project Timeline:

May 2007 Bond Approval

Fall 2007 Preliminary Design

Dec 2007 Schematic Design

Winter 07/08 Value Engineering/Design Development (Value Engineering is a formal method to ensure the greatest value or function in a project. A variety of professionals look at the progress of the project with a “fresh set of eyes” and make suggestions to enhance the functionality and features of the project.)

May/June 08 Construction Documents Complete

July 08 Receive State Match Funding

August 08 Begin Construction

December 09 Estimated Conclusion of Construction


THANK YOU! I can’t tell you the number of times I think of the support the voters gave last spring for the serious needs at both of our elementary schools. We are so appreciative of the “YES” vote last May which created the opportunity for us to move forward on the construction projects at Lake Spokane and Nine Mile.

We have spent the last few months finalizing the design phase of each project. It is important to note that we will be doing these two projects simultaneously beginning in August 2008. Each site will have preliminary work beginning right after school is out, but the major construction effort can not begin until we receive our “State match” dollars. We are not eligible to apply for those until July 1, 2008. The budget for these combined projects is $18,350,000 which includes the $12,350,000 approved by voters and approximately $6,000,000 the State will provide in matching dollars now that the voters have said “YES.”

At Lake Spokane we are excited for the new square footage. Over 25,000 square feet of new construction will be added to the building. As a result, the portables will be removed and new construction will replace that area and an additional wing across the back of the school will include a new music room and new classrooms. Renovation will also occur in much of the remaining building. The much needed space will be provided in both the office and staff lunch/work areas. Additionally, there will be classrooms available for future growth, a new library and computer lab, a cohesive Special Education area, a new HVAC system, and a beautiful courtyard for use by our younger children. A paved parking lot for parent drop off and event parking will be an added benefit from the project.

At Nine Mile we will gain over 3000 square feet in new construction as well as renovation of a large part of the building. The construction area will be a new library and computer lab. Additionally, the music and band area will be modernized with storage available for both programs. The Special Education area, office/staff work room area, and some classrooms will be completely renovated as well. A paved parking lot and event parking will also be a highly welcome attribute to the Nine Mile Elementary project.

The Design Teams in each building (including staff, parents, board members, and administrators) are actively working their way through some of the finer details of the project. Their input is critical to the successful completion of these projects, and we are very thankful for their participation.

Please feel free to call with any questions regarding these two projects. Their success is important to the future of not only Nine Mile Falls School District, but the community as well. Once again, thank you for your “YES” vote that made it possible to meet our kids needs.

Lake Spokane Elementary
Tenative plans in pdf format

LSE Design Committee
Scott Fischer
Jared Smith
Tom Mercer
Craig Leone
Jeff Jurgensen
Kevin Simpson
Phyllis Schaeffer
Colleen Guyette
Diana Frazier
Janie Johnson
Sandy Nuechterlein
Judy Payne
Holly Kimm
Colleen Weisser
Mandolyn Hume
Marc Bell
Floyd Smith
Bridget Lewis
Vicki Daggy
Scott Chaney
Steve Roth

Nine Mile Falls Elementary
Tenative plans in pdf format

NMFE Design Committee
Scott Fischer
Jared Smith
Tom Mercer
Craig Leone
Jeff Jurgensen
Len Mortlock
Karen Coburn
Carolyn Brady
Barb McCray
Dawn Toelken
Joy Murphy
Marc Bell
Floyd Smith
Bridget Lewis
Rose Theisen
Michael Hartman
Erica Carden

 

 


Main
Superintendent's Welcome
Eye On Education
Calendar/Events
Teaching and Learning
School Board
Student Services
Staff Directory
Lunch Menu
Annual Report
Employment
Our Community
Student Transportation
Public Notices

Bond Update

Our Schools
Nine Mile Elementary
Lake Spokane Elementary
Lakeside Middle
Lakeside High